NBB October 31, 2014: BOOERWERY Site Update

By on October 31, 2014

NBB-impact-graphics-4

HAPPENING NOW

NBB-impact-graphics-4Deep Foundation Piles
Anticipated neighborhood impact: 4 of 5 (noise and trucks)
The second and final planned installation of deep foundation piles will start around November 10 and be finished within two weeks or less, weather pending. We thank our immediate neighbors for their patience during this process.

Given the generally unstable soil conditions of our site, certain sections of the brewery and all of the Liquid Center must rely on deep foundation piles, i.e. steel H-beams driven into the ground until reaching bedrock.  This process is loud, with ground vibration being felt by neighbors closest to the site. We’ve contracted a local geotechnical firm to monitor noise and vibration levels along the perimeter of our site during this process.

NBB-impact-graphics-2Pre-Cast Wall Arrival and Setting
Anticipated neighborhood impact: 2 of 5 (truck deliveries)
Starting in early November, our precast walls for our kegging and packaging halls will arrive by truck on Haywood Road with an average of about 5 trucks per day over about a three week period.

Steel Delivery
Anticipated neighborhood impact: 2 of 5 (truck deliveries)
By mid-November, our first delivery of structural building steel will arrive.

Brew House and Cellar Foundations
Anticipated neighborhood impact: 2 of 5 (concrete trucks)
Foundation work runs through the first of next year.  We are forming the Brew House deck now and expect to pour the deck on November 14, 2014.

Saturday, November 14 – Morning Concrete Pour
P
otential of an early start, with the process starting around 5 a.m.

Thank you for your patience with us during the morning cellar deck concrete pour on October 18.

Malt Silos Preparation
Malt Silos store malt for brewing and construction continues through November.

LOOKING AHEAD

  • Setting steel for roof and second and third floors at Brew House after Thanksgiving
  • Brew House and Fermentation vessels set in early 2015

 

The City is making improvements to Craven Street through summer 2015.  There will be street closures and delays.  More information.